UNUSUAL EVENT AND PLANT SHUTDOWN DUE TO DRYWELL UNIDENTIFIED LEAKAGE GREATER THAN 10 GPM
"At 0152 [EDT], Nine Mile Point Unit 2 received red alarms for containment monitoring cabinets 10A and 10B along with a rise in drywell floor drain leakage and drywell pressure.
"At 0205 [EDT], Nine Mile Point Unit 2 entered technical specification action statement (TS 3.4.5 B) due to unidentified leakage rise of greater than 2 gpm within 24 hours.
"At 0217 EDT, the control room commenced power reduction to mitigate the rise in drywell leakage and drywell pressure.
"At 0322 EDT, Nine Mile Point Unit 2 declared an Unusual Event (EAL 2.1.1) due to unidentified drywell leakage greater than 10 gpm. Actual drywell floor drain leakage reached 11.3 gpm.
"The cause of the rise in unidentified leakage is unknown at this time.
"At 0345 EDT, Nine Mile Point Unit 2 has commenced a plant shutdown."
The licensee has notified State and local authorities. The NRC Resident Inspector has been notified.
Apparently the Unit 2 reactor was restarted but had to be shut down again Thursday morning (8/11/2011) due to a different leak in a feedwater pump.NEW YORK, Aug 9 (Reuters) - Constellation Energy Nuclear Group completed the repairs on the 1,148-megawatt Unit 2 at the Nine Mile Point nuclear power plant in New York and were doing post maintenance testing, a spokeswoman for the plant said Tuesday.She could not say when the unit, which shut over the weekend, would return to service.Electricity traders guessed it would restart over the next day or so....